Timeline Planning

skill-britt-claude-code-skills-timeline-planning · by britt

Use when asked for a project timeline, schedule, sprint plan, or Gantt chart, or after breaking work into issues - converts issue estimates and dependencies into a Mermaid Gantt chart with phases, milestones, and critical path

No reviews yet
0 installs
13 views
0.0% view→install

Install

$ agentstack add skill-britt-claude-code-skills-timeline-planning

✓ scanned · ✓ verified — works with Claude Code, Cursor, and more.

Security review

✓ Passed

No issues found. Passed automated security review. · v0.1.0 How review works →

  • Prompt-injection patterns
  • Secret / credential exfiltration
  • Dangerous shell & filesystem operations
  • Untrusted network calls
  • Known-malicious package signatures

What it can access

  • Network access No
  • Filesystem access No
  • Shell / process execution No
  • Environment & secrets No
  • Dynamic code execution No

From automated source analysis of v0.1.0. “Used” means the capability is present in the source — more access means more to trust, not that it’s unsafe.

Are you the author of Timeline Planning? Claim this listing to set pricing, connect Stripe payouts, and keep 70% of every sale.
Sign up to claim

About

Timeline Planning Skill

Generate Mermaid Gantt charts that visualize project timelines, task scheduling, phases, and milestones based on GitHub issues and their estimates.

When to Use

Activate this skill when:

  • User asks "what would the timeline look like?"
  • User says "create a Gantt chart", "show me the project schedule"
  • After running the issue-decomposition skill, to visualize scheduling of the resulting issues
  • During sprint planning to allocate work

Mermaid Gantt Syntax

Basic Structure

gantt
    title Project Timeline
    dateFormat YYYY-MM-DD

    section Phase 1
    Task A :a, 2025-01-15, 2d
    Task B :b, after a, 3d

    section Phase 2
    Task C :c, after b, 2d

Key Elements

  • title - Chart title
  • dateFormat - How dates are parsed
  • section - Groups related tasks
  • Task format: Name :id, start, duration

Estimate to Duration Conversion

Convert T-shirt size estimates to days:

| Estimate | Duration | Notes | |----------|----------|-------| | Small | 1d | Single-day task | | Medium | 3d | Few days of work | | Large | 5d | Almost a week | | XL | 8d | Full week+ |

Adjust based on team velocity, complexity indicators, and buffer for unknowns.

Task States

| Modifier | Meaning | Example | |----------|---------|---------| | done | Completed | Task A :done, a, 2025-01-15, 2d | | active | In progress | Task B :active, b, after a, 3d | | crit | Critical path | Task C :crit, c, after b, 5d | | milestone | Milestone | MVP :milestone, m, after c, 0d |

Timeline Patterns

Reusable Gantt patterns (linear project, parallel workstreams, milestones, critical path) are in [gantt-patterns.md](gantt-patterns.md).

Timeline Generation Process

Step 1: Gather Issues

Prerequisite: fetch the open issues with gh issue list --state open --json number,title,labels,body (requires the gh CLI), or ask the user to paste the issue list.

Gather the following from project issues:

  • Issue titles
  • Estimates or labels indicating size
  • Dependencies or blocking relationships

Step 2: Determine Start Date

  • Use today's date as default start
  • Or ask user for preferred start date
  • Consider sprint boundaries

Step 3: Convert Estimates

Transform issue estimates to durations:

#101 [Small] → 1d
#102 [Medium] → 3d
#103 [Large] → 5d

Step 4: Respect Dependencies

Order tasks based on blocking:

#101 → start immediately
#102 blocked by #101 → after #101
#103 blocked by #102 → after #102

Step 5: Group into Phases

Organize tasks into logical sections: Setup/Foundation, Core Features, Testing, Polish.

Step 6: Generate Gantt Chart

Create the Mermaid syntax with all tasks, dependencies, and phases.

Date Formats

| Format | Example | |--------|---------| | YYYY-MM-DD | 2025-01-15 | | after id | after a | | Nd | 3d - duration in days |

Best Practices

  1. Use sections - Group related tasks for clarity
  2. Show dependencies - Use after id to chain tasks
  3. Mark milestones - Highlight key deliverables
  4. Indicate critical path - Use :crit for must-do-first tasks
  5. Keep titles short - Fit in the chart view
  6. Add buffer - Include slack for unknowns

Example Output

For a set of issues about user authentication:

gantt
    title User Authentication System
    dateFormat YYYY-MM-DD

    section Foundation
    Setup auth module       :a, 2025-01-20, 1d
    Database schema         :b, after a, 1d

    section Core Auth
    Registration endpoint   :c, after b, 3d
    Login endpoint          :d, after b, 3d
    Password reset          :e, after c, 2d

    section Security
    JWT implementation      :f, after d, 2d
    Rate limiting           :g, after f, 1d

    section Testing
    Unit tests              :h, after e g, 2d
    Integration tests       :i, after h, 2d

    section Milestone
    Auth Complete           :milestone, m1, after i, 0d

Handling Edge Cases

No Estimates

If issues lack estimates:

  • Use Medium (3d) as default
  • Flag for user to review

Circular Dependencies

If dependencies form a loop:

  • Error and ask user to resolve
  • Cannot generate valid timeline

Too Many Tasks

If > 20 tasks:

  • Group into summary tasks
  • Suggest breaking into phases

After Generating Timeline

  • Show total project duration
  • Identify the end date
  • Flag if timeline exceeds any stated deadlines
  • Offer to save the chart to a markdown file in the repo
  • Suggest adding milestones if missing

Source & license

This open-source skill is cataloged on AgentStack and links to its original source — we do not rehost the code.

Install and usage instructions live in the source repository linked above.

Reviews

No reviews yet — be the first.

Versions

  • v0.1.0 Imported from the upstream source.