Install
$ agentstack add skill-jayrha-agentskills-project-planner ✓ scanned · ✓ verified — works with Claude Code, Cursor, and more.
Security review
✓ PassedNo issues found. Passed automated security review. · v0.1.0 How review works →
- ✓ Prompt-injection patterns
- ✓ Secret / credential exfiltration
- ✓ Dangerous shell & filesystem operations
- ✓ Untrusted network calls
- ✓ Known-malicious package signatures
What it can access
- ✓ Network access No
- ✓ Filesystem access No
- ✓ Shell / process execution No
- ✓ Environment & secrets No
- ✓ Dynamic code execution No
From automated source analysis of v0.1.0. “Used” means the capability is present in the source — more access means more to trust, not that it’s unsafe.
About
Project Planner
Overview
Turns a fuzzy goal into a concrete, scheduled plan. Produces a Work Breakdown Structure (WBS), milestones, an explicit dependency graph, defensible effort estimates, a critical path, and a risk register.
Keywords: project plan, work breakdown structure, WBS, milestones, dependencies, critical path, estimation, scheduling, roadmap, task decomposition, Gantt, sequencing.
Use this skill whenever the input is a goal/spec/idea and the desired output is "what needs to happen, in what order, and roughly how long".
When to use
- "Plan the migration to X" / "Break this feature into tasks" / "Build a roadmap for Q3".
- The user has a deliverable but no task list, sequence, or estimate.
- An existing task list needs dependencies, estimates, or a critical path added.
Workflow
Follow these steps in order. Do not skip clarification.
- Clarify the goal and constraints. Capture: the single end deliverable ("done" definition), hard deadline (if any), team/resource availability, and any fixed external dependencies. Ask at most 3–5 sharp questions if these are missing. See
references/clarifying-questions.md. - Decompose into a WBS. Break the goal top-down into deliverable-oriented work packages using the 100% rule (children fully cover the parent, no overlap). Stop decomposing at the 8/80 rule: each leaf task is 8–80 hours of work. Number hierarchically (1, 1.1, 1.1.1). See
references/wbs-method.md. - Define milestones. Mark zero-duration checkpoints that signal a meaningful state change (e.g., "Design approved", "Beta deployed"). Every milestone must map to completed work packages.
- Map dependencies. For each leaf task list its predecessors and the dependency type (FS/SS/FF/SF, default Finish-to-Start). Distinguish hard (mandatory) from soft (preferred) dependencies. See
references/dependencies-and-critical-path.md. - Estimate effort. Estimate each leaf task using three-point PERT:
te = (O + 4M + P) / 6. Record Optimistic/Most-likely/Pessimistic. Convert effort to duration using availability and parallelism. Seereferences/estimation.md. - Compute the schedule and critical path. Forward pass for early start/finish, backward pass for late start/finish, slack = LS − ES. The critical path is the zero-slack chain; its length is the minimum project duration. Use
scripts/critical_path.pyto compute this automatically from your task list. - Identify risks. List top risks with likelihood × impact, and a mitigation or contingency buffer for each. Add schedule buffer to the critical path, not to individual tasks.
- Produce the plan document. Fill in
templates/project-plan.md. Present the WBS, milestone table, dependency/critical-path summary, estimate table, and risk register.
Estimation quick reference
- Always estimate effort (person-hours) separately from duration (calendar time). Duration = effort ÷ (people × daily-available-hours), inflated by dependencies and context-switching.
- Use PERT three-point estimates; never a single number for anything non-trivial.
- Apply a global contingency buffer (typically 15–30%) at the project level based on novelty, not per-task padding.
- Decompose anything you cannot estimate confidently — uncertainty is a signal the task is too big.
Decision heuristics
- Too big to estimate? Split it (8/80 rule).
- More than ~7 children under one parent? Add an intermediate grouping level.
- A task everyone depends on? It is likely on the critical path — protect it and start it early.
- Long pole with high uncertainty? Prototype/spike it first as its own early task to retire risk.
- Soft dependency blocking parallelism? Challenge it; reordering may shorten the critical path.
Best Practices
- Decompose by deliverables and outcomes, not by activities or org charts.
- Every leaf task has a verb, a clear "done" criterion, an owner (or role), an estimate, and predecessors.
- Make dependencies explicit; an implicit dependency is a missed delay.
- Re-estimate and recompute the critical path whenever scope changes.
- Keep the WBS and the schedule in sync; the schedule is derived from the WBS, never invented separately.
Common Pitfalls
- Confusing milestones with tasks (milestones have zero duration).
- Padding every task instead of buffering the project — hides real slack and invites Parkinson's Law.
- Listing tasks with no dependencies, producing a flat "everything at once" plan.
- Estimating duration directly and forgetting that one person can't do two parallel tasks.
- Decomposing by team ("Frontend work") rather than by deliverable, causing gaps and overlaps.
- Ignoring the critical path, then compressing non-critical tasks that don't move the deadline.
Bundled files
references/wbs-method.md— decomposition rules, numbering, 100%/8-80 rules, worked breakdown.references/estimation.md— PERT, effort vs duration, story points, calibration.references/dependencies-and-critical-path.md— dependency types, forward/backward pass, slack, crashing/fast-tracking.references/clarifying-questions.md— the question checklist for step 1.scripts/critical_path.py— computes ES/EF/LS/LF, slack, critical path, and project duration from a JSON task list.templates/project-plan.md— the output document template.examples/website-launch.md— a full worked example from goal to scheduled plan.
Source & license
This open-source skill is cataloged on AgentStack and links to its original source — we do not rehost the code.
- Author: JayRHa
- Source: JayRHa/AgentSkills
- License: MIT
Install and usage instructions live in the source repository linked above.
Reviews
No reviews yet — be the first.
Write a review
Versions
- v0.1.0 Imported from the upstream source.